Town & County

SNAPPED: PC MARC Aquatic Facility Renovation in Full Swing

PARK CITY, Utah — Renovation of the outdoor aquatic facilities at the PC MARC is on track for a summer 2026 reopening, according to Park City Municipal.

Workers make progress on the renovated pool complex at the PC MARC, expected to reopen by summer 2026. Photo: Tanzi Propst/Park City Municipal Corporation 2026

The project includes a new eight-lane lap pool, zero-entry access, a slide, and a rock climbing wall.

Structural work is underway at the PC MARC as part of the outdoor aquatic facility renovation. Photo: Tanzi Propst/Park City Municipal Corporation 2026

Construction began in April 2025, following the Park City Council’s 2023 approval of funding and its November 2024 approval of the final design. Additional funding was approved in March 2025 to secure Northridge Construction as the contractor.

The PC MARC pool renovation project includes a new eight-lane lap pool, slide and rock climbing wall. Photo: Tanzi Propst/Park City Municipal Corporation

According to a recent city update, lap pool demolition is complete, utility work is nearly finished, and structural work is underway on the pump house, slide, and climbing wall. Aquatic programming will resume once construction is complete.

The outdoor aquatic facility at the PC MARC takes shape ahead of a planned summer 2026 reopening. Photo: Tanzi Propst/Park City Municipal Corporation 2026

The lap pool area remains closed during construction, though the city says access to the tennis courts will continue throughout the project.

TownLift Is Brought To You In Part By These Presenting Partners.
Advertisement

Add Your Organization

298 views